At a location in Tilburg, M.J. van Riel carried out three assignments simultaneously.

The first task was to tip and place a tank, accompanied by a separate drip tray. Two truck-mounted cranes, in collaboration, completed this task.

At the same site, a little further along, a 70-tonne telescopic crane, in three deployments, placed the chimney for a filter plant.

On the other side of the company, we assisted in assembling screw jacks, using a 50-tonne telescopic crane. These screw jacks had a length of 20 metres.

The successful execution of these three assignments not only demonstrates our versatility but also highlights the competence of our team.

Facebook
Twitter
LinkedIn
WhatsApp
Email

Latest News

Complex logistics operation carried out with only 3 cm of clearance

Complex logistics operation carried out with only 3 cm of clearance

In December, we successfully completed a complex logistics operation on behalf of FB Group, combining precision, experience, and heavy equipment.
M.J. van Riel B.V. takes over all activities of Martens Transport Oosterhout B.V.

M.J. van Riel B.V. takes over all activities of Martens Transport Oosterhout B.V.

M.J. van Riel is delighted to announce that it reached an agreement last Friday to acquire all Martens Transport activities.…
Two storage tanks safely moved and prepared for transport by water

Two storage tanks safely moved and prepared for transport by water

M.J. van Riel recently completed a unique lifting and transport project for a leading client: the careful relocation of two…