Day 1: unloading and transporting the drum
On day 1, the drum arrived by inland vessel from Germany. On site, we unloaded the 160-tonne load using our 700-tonne telescopic cranes and then placed it on our Self-Propelled Modular Transporter (SPMT). This allowed us to drive the drum safely and in a controlled manner to the correct location on the site.
Day 2: hoisting and positioning
The next day was devoted to hoisting and precisely positioning the drum. This precise work required not only the right equipment, but also close coordination between our crane operators and transport team. Thanks to the right preparation, this phase also went smoothly.
Teamwork and precision
This two-day project is a fine example of what we at M.J. Van Riel can achieve together. Thanks to good teamwork, craftsmanship and reliable equipment, we deliver complete solutions for hoisting, heavy transport and machine relocation throughout the Netherlands.